powered help
header-left header-center header-right
File #: 121752    Version:
Type: Resolution Status: Passed
File created: 4/9/2013 In control: COMMON COUNCIL
On agenda: Final action: 4/30/2013
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,014,100 for a total estimated cost of $3,312,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 75 Committee Actions, 3. Official Notice Number 75, 4. Hearing Notice List, 5. Notice Published on 5-16-13
Number
121752
Version
SUBSTITUTE 1
Reference
091621
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,014,100 for a total estimated cost of $3,312,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $3,014,100. The total estimated cost of these projects is $3,312,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

1st Aldermanic District

N. 19th St. - W. Capitol Dr. to W. Olive St. (ST211120121) File Number 091621: Pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6-11 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $21,200; Nonassessable Reconstruction Paving Fund -- $360,000). The total estimated cost for this project including the requested amount is $400,000. This project is anticipated to be completed during the 2014 construction season.

3rd and 6th Aldermanic Districts

E. Wright St. - N. Humboldt Blvd. to N. Holton St. (ST211070141) File Number 121550: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (3-4 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $18,400; Nonass...

Click here for full text