powered help
header-left header-center header-right
File #: 111170    Version: 0
Type: Resolution Status: Passed
File created: 12/20/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/18/2012
Effective date:    
Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $8,930,000 for a total estimated cost of these projects being $9,907,000.
Sponsors: THE CHAIR
Indexes: SANITARY SEWERS, SEWER IMPROVEMENTS, STORM SEWERS
Attachments: 1. Hearing Notice List
Number
111170
Version
ORIGINAL
Reference
101095
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $8,930,000 for a total estimated cost of these projects being $9,907,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $8,930,000. The total estimated cost of these projects is $9,907,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

W. Roosevelt Dr. (south side) - N. Teutonia Ave. to N. 22nd St. (SM495100244) File Number 101095: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $156,000). The total estimated cost for this project including the requested amount is $171,000. This project is anticipated to be completed during the 2012 construction season.

W. Roosevelt Dr. - N. 27th St. to N. 30th St. (SM495100247) File Number 101095: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $490,000). The total estimated cost for this project including the requested amount is $505,000. This project is anticipated to be completed during the 2012 construction season.

3rd and 6th Aldermanic Districts

E. Chambers St. - N. Richards St. to N. Humboldt Blvd. (SM495110016) File Number 101439: Combined large diameter sewer lining and lining. (Nonassessable Sewer Maintenance Relay Fund -- $715,000). The total estimated cost for this project including the requested amount is $745,000. ...

Click here for full text