powered help
header-left header-center header-right
File #: 240278    Version:
Type: Resolution Status: In Council-Adoption
File created: 6/11/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $110,000 for a total estimated cost of these projects being $1,100,000.
Sponsors: THE CHAIR
Number
240278
Version
Proposed Substitute 1
Reference
231828
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $110,000 for a total estimated cost of these projects being $1,100,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $110,000 with the total cost estimated to be $1,100,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

7th Aldermanic District

N. Sherman Blvd. - W. Burleigh St. to W. Capitol Dr. (SM499240024) File Number 231828; Installing bioswales. (Nonassessable Water Quality Fund -- $50,000 additional funding). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2026 construction season.

7th and 15th Aldermanic District

N. Sherman Blvd. - W. North Ave. to W. Burleigh St. (SM499240023) File Number 231828; Installing bioswales. (Nonassessable Water Quality Fund -- $50,000 additional funding). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2026 construction season.

14th Aldermanic District

S. Shore Dr. - E. Texas Ave. to E. Meredith St. (ST211240154) Permeable pavement reconstruction and grading. (Nonassessable Reconstruction Paving Fund -- $10,000) The total estimated cost of this project including the requested amount is $500,000. This project is anticipated to be complet...