File #: 240649    Version: 0
Type: Resolution Status: Passed
File created: 9/3/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/24/2024
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of West Silver Spring Drive (6 Intersections) with a total estimated cost increase for the project of $98,395.40, with an estimated Grantor share of $0, and an estimated City share of $98,395.40.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Resolution Certification 2090-16-00.pdf

Number

240649

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of West Silver Spring Drive (6 Intersections) with a total estimated cost increase for the project of $98,395.40, with an estimated Grantor share of $0, and an estimated City share of $98,395.40.

Analysis

Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of West Silver Spring Drive (6 Intersections) with a total estimated cost increase for the project of $98,395.40, with an estimated Grantor share of $0, and an estimated City share of $98,395.40.

Body

Whereas, Additional funds are, therefore, necessary to complete the construction of the projects; now, therefore be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

 

Project Grant Value

State ID 2090-16-00

ST320210501

West Silver Spring Drive

6 Local Intersections

 

City Share Non-Assessable Paving Fund

ST320240000

Fund 0333

$98,395.40

 

Grantor Reimbursable

SP032240100

Fund 0306

$0

 

Grantor Non-Reimbursable

$ 0

 

Total Preliminary Engineering $98,395.40

 

Previously Authorized for Preliminary Engineering $281,000

Current estimated cost of total project including this resolution $3,059,528.30

Original estimated cost of total project (Resolution File Number 201664) $1,417,715

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA:K. Vos