powered help
header-left header-center header-right
File #: 191128    Version: 0
Type: Resolution Status: Passed
File created: 11/5/2019 In control: COMMON COUNCIL
On agenda: Final action: 11/26/2019
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to the previously established project accounts for the Wisconsin Department of Transportation and the City of Milwaukee for funding participation for preliminary engineering costs associated with two projects in two Aldermanic districts with a total estimated cost increase for the projects of $37,000, with $5,000 being Grantor-funded and $32,000 being City-funded.
Sponsors: THE CHAIR
Indexes: COMPTROLLER, PUBLIC IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Capital Grant Resolution Certification 1, 2. Capital Grant Resolution Certification 2
Number
191128

Version
ORIGINAL

Reference

Sponsor
THE CHAIR

Title
Resolution authorizing the City Comptroller to transfer additional funds to the previously established project accounts for the Wisconsin Department of Transportation and the City of Milwaukee for funding participation for preliminary engineering costs associated with two projects in two Aldermanic districts with a total estimated cost increase for the projects of $37,000, with $5,000 being Grantor-funded and $32,000 being City-funded.

Analysis
Resolution authorizing the City Comptroller to transfer additional funds to the previously established project accounts for the Wisconsin Department of Transportation and the City of Milwaukee for funding participation for preliminary engineering costs associated with two projects in two Aldermanic districts with a total estimated cost increase for the projects of $37,000, with $5,000 being Grantor-funded and $32,000 being City-funded.

Body
Whereas, Unanticipated preliminary engineering costs have resulted in increased costs charged against two capital improvement projects; and

Whereas, Additional funds are, therefore, necessary to complete the preliminary engineering for the two projects; now, therefore be it

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

Project Grant Value
Project ID 2984-06-06
BR320141301 and ST320141301
West Brown Street Bridge over CP RR

City Share Non- Assessable Fund Structure
BR300190000
Fund 0303
$32,000

Previously authorized for engineering: $416,880.
Current estimated cost of total project including this resolution: $3,078,470.
Original estimated cost of total project (File Number 140427): $3,046,470.

Project Grant Value
Project ID 2030-15-00
ST320180701
North Lovers Lane Road Bridge B-40-0435
Over Union Pacific Railroad

Grantor Reimbursable Fund Structure
SP032190100
Fund 0306
$5,000

T...