powered help
header-left header-center header-right
File #: 240614    Version:
Type: Resolution Status: Passed
File created: 9/3/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/24/2024
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $170,000 for a total estimated cost of these projects being $2,322,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/30/20241 MAYOR SIGNED   Action details Meeting details Not available
9/24/20241 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
9/11/20240 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Appearing: Holly Rutenbeck, DPW Ald. Brostoff moved substitution of the file with Proposed Substitute A. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
9/11/20241 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
9/3/20240 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
240614
Version
SUBSTITUTE 1
Sponsor
THE CHAIR

Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $170,000 for a total estimated cost of these projects being $2,322,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $170,000 with the total cost estimated to be $2,322,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

7th Aldermanic District

N. 29th St. - W. Concordia Ave. to W. Townsend St. (SM495240029) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund --$20,000). The total estimated cost of this project including the requested amount is $322,000. This project is anticipated to be completed during the 2024-2025 construction season.

City Wide

ADA ramps for 2025 High impact paving north-side projects: (ST216240111) Replace curb and gutter and sidewalk as necessary (Nonassessable High Impact Paving Fund - $75,000). The total estimated cost of this project including the requested amount is $1,000,000. This project is anticipated to be completed during the 2025 construction season.

ADA ramps for 2025 High impact paving south-side projects: (ST216240112) Replace curb and gutter and sidewalk as necessary (Nonassessable High Impact Paving Fund - $75,000). The total estimated cost of this project including the requested amount is $1,000,000. This project is anticipated to be completed during the 2025 construction season.

;and, be it

Further Resolved, That all Cit...

Click here for full text