Resolution relative to the cost participation and installation of traffic signal improvements at six connecting highway intersections on West Forest Home Avenue and South 27th Street under a Highway Safety Improvement Program project in the 8th and 11th Aldermanic Districts at a total estimated cost of $318,994.83, with an estimated grantor share of $273,465.00, and an estimated City share of $45,529.83.
Analysis
Resolution relative to the cost participation and installation of traffic signal improvements at six connecting highway intersections on West Forest Home Avenue and South 27th Street under a Highway Safety Improvement Program project in the 8th and 11th Aldermanic Districts at a total estimated cost of $318,994.83, with an estimated grantor share of $273,465.00, and an estimated City share of $45,529.83, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the entire project is $1,104,494.83, with a grantor share of $859,410, and a City share of $245,084.83.
Body
Whereas, A State Municipal Agreement for the installation of traffic signal improvements at the six connecting highway intersections under the 2018 Highway Safety Improvement Program was approved by the Common Council under File Number 140654; and,
Whereas, The Highway Safety Improvement Program provides cost participation for traffic signal and other improvements to reduce the frequency and severity of vehicle and pedestrian crashes; and
Whereas, Six intersections on West Forest Home Avenue and South 27th Street have been identified for traffic signal improvements; and
Whereas, The total estimated cost of this project is $295,365.58 for the installation of traffic signal improvements; and
Whereas, The total estimated cost for state review for the pr...