Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $225,000 for a total estimated cost of these projects being $696,000.
Sponsors: THE CHAIR
Attachments: 1. Prop Sub A

Number
250756
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $225,000 for a total estimated cost of these projects being $696,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $225,000 with the total cost estimated to be $696,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

6th Aldermanic District

N. 6th St. – 250’ +/- south of W. Vienna Ave. to W. Vienna Ave. (SM495250044) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of the project including the requested amount is $88,000. This project is anticipated to be completed during the 2026 construction season.

W. Concordia Ave. – N. 9th St. to N. 10th St. (SM495250042) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of the project including the requested amount is $89,000. This project is anticipated to be completed during the 2026 construction season.

W. Concordia Ave. – N. 11th St. to N. 12th St. (SM495250043) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of the project including the requested amount is $88,000. This project is anticipated to be completed during the 2026 construction season.

8th Aldermanic District

27th Street Viaduct (400 North) (BR100250114) Bridge expansion joint replacement. (City Share No...