Number
110245
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of traffic signal improvements on West North Avenue at North 7th Street and at North 8th Street under a Highway Safety Improvement Program project in the 6th and 15th Aldermanic Districts at a total estimated cost of $49,039.27, with an estimated grantor share of $44,135.34, and an estimated City share of $4,903.93.
Analysis
Resolution relative to the cost participation and installation of traffic signal improvements on West North Avenue at North 7th Street and at North 8th Street under a Highway Safety Improvement Program project in the 6th and 15th Aldermanic Districts at a total estimated cost of $49,039.27, with an estimated grantor share of $44,135.34, and an estimated City share of $4,903.93, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the project is $70,000, with an estimated grantor share of $63,000, and an estimated City share of $7,000.
Body
Whereas, A Project Agreement for the installation of traffic signal improvements on West North Avenue at North 7th Street and at North 8th Street under the 2011 Highway Safety Improvement Program (HSIP) was approved by the Common Council under File Number 090888; and
Whereas, The HSIP is intended to reduce the number and severity of vehicle and pedestrian crashes; and
Whereas, The total estimated cost of the project is $49,039.27 for traffic control signal improvements; and
Whereas, $4,903.93 is not reimbursable and is included in the Division’s 2011 Capital Purpose Project/Grant Number ST320110000; and
Whereas, $44,135.34 is reimbursable from the Wisconsin Department of Transportation (WISDOT), and should be earmarked for this project in the 2011 Capital Grant and Aids Projects Fund Project/Grant ...
Click here for full text