powered help
header-left header-center header-right
File #: 191887    Version:
Type: Resolution Status: Passed
File created: 3/24/2020 In control: COMMON COUNCIL
On agenda: Final action: 4/14/2020
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,228,000 for a total estimated cost of these projects being $6,198,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number
191887
Version
SUBSTITUTE 1
Reference
190743
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,228,000 for a total estimated cost of these projects being $6,198,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,228,000. The total estimated cost of these projects is $6,198,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd Aldermanic District

W. Bobolink Ave. - N. 68th St. to N. 70th St. (WT410200637) File Number 181588: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $175,000). The total estimated cost of this project including the requested amount is $190,000. This project is anticipated to be completed during the 2020 construction season.

W. Stark St. - N. 64th St to N. 67th St. (WT410200646) File Number 181588: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $305,000). The total estimated cost of this project including the requested amount is $325,000. This project is anticipated to be completed during the 2020 construction season.

N. 67th St. - W. Fond du Lac Av. to W. Stark St. (WT410200647) File Number 181588: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $220,000). The total estimat...

Click here for full text