Title
Substitute resolution authorizing area-wide and scattered sites sidewalk replacement at various areas and appropriating funds for these purposes with the city construction cost estimated to be $850,000 for a total estimated cost of these projects being $950,000.
Analysis
To provide the necessary authority for sidewalk repairs at various areas. The City cost of these projects approved by this resolution is estimated to be $850,000. The total estimated cost of these projects is $950,000.
Whereas, It is necessary and in the public interest to replace those sidewalk stones which are cracked, broken, out of grade or otherwise a hazard to pedestrians; and
Whereas, It is proposed that sidewalk replacement work be done in the following locations at the indicated cost:
3rd and 12th Aldermanic Districts
Area bounded by: N. Downer Ave., E. Belleview Pl., N. Lake Dr. and E. Park Pl. and Area bounded by: W. Mitchell St., S. 7th St., W. Windlake Ave. and S. 11th St. (ST230220165) File Number 211199: Laying concrete walk. Doing all necessary grading pertaining to said work. (Assessable Sidewalk Reconstruction Paving Fund -- $125,000; Nonassessable Sidewalk Reconstruction Paving Fund -- $325,000). The total estimated cost for this project including the requested amount is $500,000. This project is anticipated to be completed during the 2022 construction season.
ADA ramps for 2022 Area wide sidewalk repair areas (ST216220106): Replace curb and gutter and sidewalk as necessary (Nonassessable High Impact Paving Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2022 construction season.
City Wide
2022 Scattered Sites (ST230220166) File Number 211199: Laying concrete walk. Doing all necessary grading pertaining to said work. (Assessable Sidewalk Reconstruction Paving Fund -- ...