Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
ANLS:
-Analysis-
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
BODY:
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
3rd Aldermanic District
N. Arlington Pl. - E. Brady St. to E. Kane Pl. ST21190174 (873-0767-1) File Number 911748: Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $148,855; Assessable Reconstruction Paving Fund -- $55,465)
N. Fratney St. - E. Center St. to E. Hadley St. ST21190223 (879-0867-9) File Number 970997: Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, grading, and tree removal where necessary. (Nonassessable Reconstruction Paving Fund -- $94,810; Assessable Reconstruction Paving Fund -- $13,615)
N. 1st St. - W. Capitol Dr. to 200 ft. m/l north of W. Capitol Dr. ST21190237 (879-0892-5) File Number 980620: New concrete pavement construction, replace curb and gutter and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $28,755; Assessable Reconstruction Paving Fund -- $10,130; Glendale -- $12,900)
10th Aldermanic District
Alley between W. Chambers St., W. Locust St., N. 38th St., and N. 39th St. ST21290136 (888-0677-5) Fil...