Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $378,800 for a total estimated cost of $399,600.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Signed Letter.pdf
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
2/19/20201 MAYOR SIGNED   Action details Meeting details Not available
2/11/20201 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/29/20201 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 5th Aldermanic District W. Locust St. - N. 81st St. to N. 84th St. (ST211150137). Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 7’ width of tree border area), and grading. Ald. Borkowski moved approval. (Prevailed 5-0) 6th Aldermanic District N. 15th St. - W. Nash St. to W. Atkinson Ave. (ST211190153). Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 5-0) N. 16th St. - W. Keefe Ave. to W. Nash St. (ST211190154). Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0) 7th Aldermanic District N. 39th St. - W. Fiebrantz Ave. to W. Hope Ave. (ST211190156). Install traffic calming speed hump(s). Ald. Murphy moved approval. (Prevailed 5-0) 12th Aldermanic District W. Arthur Ave. - S. 11th St. to S. 13th St. (ST211190165). Install traffic calming speed hump(s). Ald. Borkowski moved approval. (Prevailed 5-0) W. Harrison Ave. - S. 10th St. to S. 13th St. (ST211190167). Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0) W. Scott St. - S. 18th St. to S. 20th St. (ST211190168). Install traffic calming speed hump(s). Ald. Murphy moved approval. (Prevailed 5-0) 14th Aldermanic District E. Warnimont Ave. - S. Brust Ave. to S. Clement Ave. (ST211190170). Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
1/21/20200 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
191554
Version
SUBSTITUTE 1
Reference
140037
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $378,800 for a total estimated cost of $399,600.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $378,800. The total estimated cost of these projects is $399,600.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

5th Aldermanic District

W. Locust St. - N. 81st St. to N. 84th St. (ST211150137) File Number 140037: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 7’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $9,300; Nonassessable Reconstruction Paving Fund -- $275,000). The total estimated cost of this project including the requested amount is $305,000. This project is anticipated to be completed during the 2020 construction season.

6th Aldermanic District

N. 15th St. - W. Nash St. to W. Atkinson Ave. (ST211190153) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,900; Nonassessable Reconstruction Paving Fund -- $2,000). The total estimated cost of this project including the requested amount is $9,900. This project is anticipated to be completed during...