Skip to main content
powered help
header-left header-center header-right
File #: 250535    Version: 0
Type: Resolution Status: In Council-Adoption
File created: 7/15/2025 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution authorizing the Commissioner of Public Works and Comptroller to execute a 1st Revision to a State Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, and construction of a traffic signal project titled “ATC Controller & Comm Upgrade GR 9”.
Sponsors: THE CHAIR
Attachments: 1. 29842207 - Resolution for SMA Rev1 DB.pdf, 2. 29842207_SMA-Rev1.pdf
Number
250535
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works and Comptroller to execute a 1st Revision to a State Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, and construction of a traffic signal project titled “ATC Controller & Comm Upgrade GR 9”.
Analysis
Resolution authorizing the Commissioner of Public Works and Comptroller to execute a 1st Revision to a State Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, and construction of a traffic signal project titled “ATC Controller & Comm Upgrade GR 9”. Execution of the original State Municipal Agreement was authorized under File Number 220290, which also established funds for design engineering. Construction funds for this project will be established in a future resolution.
Body
Whereas, A revised project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, and construction of a traffic signal project titled “ATC Controller & Comm Upgrade GR 9” with Federal and State aid under the Congestion Mitigation and Air Quality Program (CMAQ); and

Whereas, The Department of Public Works is requesting a change in project scope by removing 12 intersections where traffic signal improvements have already constructed by separate projects, and adding 12 new intersections into this project, with the revised project limits as shown within the revised State Municipal Agreement; and

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department...

Click here for full text