Legislation Details

File #: 260867    Version:
Type: Resolution Status: In Committee
File created: 10/13/2026 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Substitute resolution authorizing area-wide and scattered sites sidewalk replacement at various areas and appropriating funds for these purposes with the city construction cost estimated to be $1,670,000 for a total estimated cost of these projects being $1,685,000.
Sponsors: THE CHAIR
Attachments: 1. Sidewalk Replacement 2026 Sub (Now Substitute 1)
Number
260867
Version
SUBSTITUTE 1
Reference
251490
Sponsor
THE CHAIR
Title
Substitute resolution authorizing area-wide and scattered sites sidewalk replacement at various areas and appropriating funds for these purposes with the city construction cost estimated to be $1,670,000 for a total estimated cost of these projects being $1,685,000.
Analysis
To provide the necessary authority for sidewalk repairs at various areas. The City cost of these projects approved by this resolution is estimated to be $1,670,000. The total estimated cost of these projects is $1,685,000.
Body
Whereas, It is necessary and in the public interest to replace those sidewalk stones which are cracked, broken, out of grade or otherwise a hazard to pedestrians; and

Whereas, It is proposed that sidewalk replacement work be done in the following locations at the indicated cost:

10th and 12th Aldermanic Districts

Area bounded by N. Hawley Rd., W. Vine St., W. Vliet St., and N. 60th St.; and Area bounded by W. Becher St., W. Burnham St., W. Windlake Ave., S. 6th St. (ST230260101) File Number 251490: Laying concrete walk. Doing all necessary grading pertaining to said work. (Assessable Sidewalk Reconstruction Paving Fund -- $350,000; Nonassessable Sidewalk Reconstruction Paving Fund -- $700,000). The total estimated cost for this project including the requested amount is $1,050,000. This project is anticipated to be completed during the 2026-2027 construction season.
City Wide

2026 Scattered Sites Maintenance (ST230260102) File Number 251490: Laying concrete walk. Doing all necessary grading pertaining to said work. (Assessable Sidewalk Reconstruction Paving Fund -- $70,000; Nonassessable Sidewalk Reconstruction Paving Fund -- $550,000). The total estimated cost for this project including the requested amount is $620,000. This project is anticipated to be completed during the 2026-2027 construction season.

Resolved, That said Commissioner of Public Works is authorized to...