powered help
header-left header-center header-right
File #: 240368    Version: 0
Type: Resolution Status: In Council-Adoption
File created: 7/2/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,817,000 for a total estimated cost of these projects being $1,913,000.
Sponsors: THE CHAIR
Number
240368
Version
ORIGINAL
Reference
230186
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,817,000 for a total estimated cost of these projects being $1,913,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,817,000. The total estimated cost of these projects is $1,913,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

9th Aldermanic District

N. 60th St. - W. Hemlock St. to City Limits (Including W. Mill Rd. to W. Green Tree Rd.) (ST216230106) File Number 230186: Asphalt pavement resurfacing and replace ADA ramps. (Nonassessable High Impact Paving Fund -- $475,000). The total estimated cost of this project including the requested amount is $485,000. This project is anticipated to be completed during the 2024 construction season.

11th Aldermanic District

S. 29th St. - W. Oklahoma Ave. to 120’ South of W. Euclid Ave. (SM495240020) File Number 231828: Relaying storm sewer. Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $531,000). The total estimated cost of this project including the requested amount is $551,000. This project is anticipated to be completed during the 2024 construction season.

13th Aldermanic District

Area Bounded By - S. 6th St. to S. 24th St. and W. Waterford Ave. to W. Ramsey Ave. (SM495240028) File Number 240366: Sewer exams. (Nonassessable Sewer Maintenance Relay Fund --$386,000...

Click here for full text