powered help
header-left header-center header-right
File #: 101440    Version:
Type: Resolution Status: Passed
File created: 3/23/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/12/2011
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $18,469,239 for a total estimated cost of these projects being $19,033,768.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SANITARY SEWERS, SEWERS
Attachments: 1. Comptroller Certificate, 2. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/18/20111 MAYOR SIGNED   Action details Meeting details Not available
4/12/20111 COMMON COUNCIL ADOPTEDPass13:0 Action details Meeting details Not available
3/31/20111 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
3/30/20110 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual appearing: Clark Wantoch, Department of Public Works-Infrastructure Proposed Substitute A accepted.
Pass5:0 Action details Meeting details Not available
3/30/20111 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/23/20110 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
101440
Version
Substitute 1
Reference
101172
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $18,469,239 for a total estimated cost of these projects being $19,033,768.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $18,469,239. The total estimated cost of these projects is $19,033,768.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

5th Aldermanic District

W. Appleton Ave. (South Side) - W. Glendale Ave. to W. Hampton Ave. (SM495110008) File Number 101172: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $112,000). The total estimated cost for this project including the requested amount is $127,000. This project is anticipated to be completed during the 2011 construction season.

Lateral Lining and Foundation Drain Disconnection/ABB (#3) (SM494110103) File Number 101439: Sanitary sewer lining. (Infiltration/Inflow Reduction Fund -- $8,999,000). The total estimated cost for this project including the requested amount is $9,000,000. This project is anticipated to be completed during the 2011 construction season.

W. Locust St. - N. 79th St. to N. 81st St. (SM495100181) File Number 100723: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $148,000). The total estimated cost for this project including the requested amount is $163,000. This project is anticipated to be comp...