powered help
header-left header-center header-right
File #: 220191    Version: 0
Type: Resolution Status: Passed
File created: 6/1/2022 In control: COMMON COUNCIL
On agenda: Final action: 6/21/2022
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,589,860 for a total estimated cost of $1,740,400.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. AD.pdf, 2. Signed Letter.pdf, 3. Signed AD.pdf, 4. Notice published 7/11/2022
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/11/20220 CITY CLERK PUBLISHED   Action details Meeting details Not available
6/24/20220 MAYOR SIGNED   Action details Meeting details Not available
6/21/20220 COMMON COUNCIL ADOPTEDPass11:0 Action details Meeting details Video Video
6/8/20220 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mohammad Ayesh - DPW - explained the projects are supported by the neighbors according with the results of the postcard survey and by the aldermanic office as well. 2nd Aldermanic District N. 63rd St. – W. Villard Ave. to W. Lawn Ave. (ST211210205) Install traffic calming speed hump(s). Ald. Borkowski moved approval. There were no objections. N. 78th St. – W. Silver Spring Dr. to W. Carmen Ave. (ST211220119) Install traffic calming speed hump(s). Ald. Hamilton moved approval. There were no objections. W. Bender Ave. – N. 77th St. to N. 80th St. (ST211220166) Install traffic calming speed hump(s). Ald. Dodd moved approval. There were no objections. 3rd Aldermanic District N. Newhall St. – E. Belleview Pl. to E. Park Pl. (ST211220128) Install traffic calming speed hump(s). Amanda Cervantes from the 3rd. District's office said that the postcard survey results were very close. Neighbors in support: Aaron Cleveland - 2613 N Newhall St Neighbors in opposition: John Bleikan - 2645 N Newhall St Christan Kramer - 2631 N Newhall St Darnell Hamilton - 2635 N Newhall St Collett Cole - 2627 N Newhall St Ald. Hamilton moved to hold the item to the call of the chair. There were no objections. 6th Aldermanic District N. 11th St. – W. Concordia Ave. to W. Keefe Ave. (ST211210251) Install traffic calming speed hump(s). Ald. Borkowski moved approval. There were no objections. N. 11th St. – W. Keefe Ave. to W. Finn Pl. (ST211210260) Install traffic calming speed hump(s). Ald. Stamper moved approval. There were no objections. N. 17th St. – W. Concordia Ave. to W. Keefe Ave. (ST211210261) Install traffic calming speed hump(s). Ald. Borkowski moved approval. There were no objections. N. 17th St. – W. Vienna Ave. to W. Atkinson Ave. (ST211210262) Install traffic calming speed hump(s). Ald. Hamilton moved approval. There were no objections. N. Fratney St. - E. Vienna Ave. to E. Capitol Dr. (ST211180195) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (12' width of tree border area), and grading. Neighbors present: Willie Karidis - Executive Director BID 25 Riverworks wanted to get some detailed information about the timeline. Mary Dziewiontkoski and Mohammad Ayesh offered to help him. Ald. Stamper moved approval. There were no objections. E. Vienna Ave. - N. Humboldt Blvd. to N. Holton St. (ST211190140) Concrete pavement reconstruction, narrowing roadway from 40' to 38', replace all curb and gutter, replace side walk and driveway approaches where necessary, narrowing sidewalk from 6' to 5', sodding (7' width of tree border area), grading, and tree removal where necessary. Ald. Hamilton moved approval. There were no objections. 7th Aldermanic District N. 53rd St. – W. Glendale Ave. to W. Hampton Ave. (ST211220125) Install traffic calming speed hump(s). Ald. Dodd moved approval. There were no objections. W. Chambers St. – N. 35th St. to N. 36th St. (ST211220126) Install traffic calming speed hump(s). Ald. Hamilton moved approval. There were no objections. 12th Aldermanic District S. 19th St. – W. Hayes Ave. to W. Lincoln Ave. (ST211220137) Install traffic calming speed hump(s). Ald. Borkowski moved approval. There were no objections.
Pass5:0 Roll call Meeting details Video Video
6/1/20220 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
220191
Version
SUBSTITUTE 1
Reference
171853
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,589,860 for a total estimated cost of $1,740,400.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,589,860. The total estimated cost of these projects is $1,740,400.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd Aldermanic District

N. 63rd St. - W. Villard Ave. to W. Lawn Ave. (ST211210205) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,850; Nonassessable Reconstruction Paving Fund -- $1,500). The total estimated cost for this project including the requested amount is $16,600. This project is anticipated to be completed during the 2022 construction season.

N. 78th St. - W. Silver Spring Dr. to W. Carmen Ave. (ST211220119) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - $3,430; Nonassessable Reconstruction Paving Fund -- $1,500). The total estimated cost for this project including the requested amount is $13,500. This project is anticipated to be completed during the 2022 construction season.

W. Bender Ave. - N. 77th St. to N. 80th St. (ST211220166) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund - ...