File #: 111479    Version: 0
Type: Resolution Status: Passed
File created: 2/28/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/20/2012
Effective date:    
Title: Resolution relative to the cost participation and installation of street lighting facilities in conjunction with the State and Federal Aid paving of West Capitol Drive from North 60th Street to North 84th Street in the 2nd, 5th, and 10th Aldermanic Districts at a total estimated cost of $256,572.15, with 100 percent of the total cost funded by the Wisconsin Department of Transportation.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, HIGHWAYS, STREET IMPROVEMENTS, STREET LIGHTING, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Comptroller's Certification, 2. Cost Analysis, 3. Revised Executed Agreement from 110985, 4. Agreement, 5. Hearing Notice List
Number
111479
Version
ORIGINAL
Reference
100328, 110985
Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of street lighting facilities in conjunction with the State and Federal Aid paving of West Capitol Drive from North 60th Street to North 84th Street in the 2nd, 5th, and 10th Aldermanic Districts at a total estimated cost of $256,572.15, with 100 percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of street lighting facilities in conjunction with the State and Federal Aid paving of West Capitol Drive from North 60th Street to North 84th Street in the 2nd, 5th, and 10th Aldermanic Districts at a total estimated cost of $256,572.15, with 100 percent of the total cost funded by the Wisconsin Department of Transportation, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the entire project is $18,783,080.00 with a grantor share of $17,194,440.00 and a City share of $1,588,640.00
Body
Whereas, The Project Agreement for the paving of West Capitol Drive from North 60th Street to North 84th Street was approved by the Common Council under File Number 100328; and

Whereas, The Surface Transportation Program provides cost participation for street lighting improvements in conjunction with the paving of highways located on the State and Federal Aid Highway System; and

Whereas, The total estimated cost of this project is $256,572.15 for the alteration and upgrade of street lighting facilities; and

Whereas, 100 percent of the participating project cost for the installation of street lighting is reimbursable from the Wisconsin Department of Tran...

Click here for full text