Number
081075
Version
ORIGINAL
Reference
Sponsor
ALD. DONOVAN
Title
Resolution approving an agreement between the City of Milwaukee Fire Department and the Wisconsin Department of Transportation to ensure that emergency response capabilities are not adversely affected by the I-94 N-S Corridor Reconstruction Project.
Analysis
This resolution approves an agreement between the City of Milwaukee Fire Department and the Wisconsin Department of Transportation to provide planning, coordination and staffing services in an effort to mitigate emergency incidents in the project area and to ensure that emergency response capabilities are not adversely affected by the I-94 N-S Corridor Reconstruction Project.
Body
Whereas, The Wisconsin Department of Transportation will be conducting an I-94 N-S Corridor Reconstruction project: and
Whereas, The project area is defined as interstates I-94, I-43 and I-894 from College Avenue on the south, Loomis Road on the west and Howard Avenue on the north; and
Whereas, The Wisconsin Department of Transportation will provide $40,000 to the Fire Department to provide planning, coordination and staffing services in an effort to mitigate emergency incidents in the project area; and
Whereas, The Fire Department will stay informed of project roadway closures and construction progress for a 2-year period commencing on November 1, 2008 and ending on December 31, 2010; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the agreement between the City of Milwaukee Fire Department and the Wisconsin Department of Transportation to ensure that emergency response capabilities are not adversely affected by the I-94 N-S Corridor Reconstruction Project, a copy of which is attached, is approved; and, be it
Further Resolved, That the City Comptroller is authorized to:
1. Commit funds within the Grant Parent Account of the 2008 Special Revenue Grant and Aid Projects fund the following amounts for the project/...