Number
211344
Substitute 1
Reference
210701
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $7,139,000 for a total estimated cost of these projects being $9,174,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $7,139,000. The total estimated cost of these projects is $9,174,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
2nd Aldermanic District
W. Medford Ave. - W. Custer Ave. to W. Sheridan Ave. (SM495210044) File Number 210701: Sanitary Sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $62,000). The total estimated cost of this project including the requested amount is $72,000. This project is anticipated to be completed during the 2022 construction season.
N. 70th St. - W. Hope Ave. to W. Congress St. (SM495210033) File Number 210059: Installing New Sanitary Sewer. (Nonassessable Sewer Maintenance Relay Fund -- $2,183,000). The total estimated cost of this project including the requested amount is $2,253,000. This project is anticipated to be completed during the 2022 construction season.
5th Aldermanic District
W. Fairmount Ave. - W. Appleton Ave. (west-side) to N. 89th St. (WT410220679) File Number 201552: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $120,000). The total estimated cost of this project including the reques...
Click here for full text