Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $4,379,000 for a total estimated cost of these projects being $24,824,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $4,379,000 with the total cost estimated to be $24,824,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
4th Aldermanic District
Highland Avenue Lift Bridge (100 West) over the Milwaukee River (BR100250113): In Depth Inspection of Lift Bridge Hydraulic, Mechanical, and Electrical Systems. (City Share Non-assessable Structure Fund - $500,000). The total estimated cost for this project is $500,000. This project is anticipated to be completed during the 2025 construction season.
4th and 6th Aldermanic District
Juneau Avenue Lift Bridge (100 East) over the Milwaukee River (BR100250106): Preliminary engineering for bridge repair. (City Share Non-assessable Structure Fund - $100,000). The total estimated cost for this project is $500,000. This project is anticipated to be completed during the 2026 construction season.
4th and 12th Aldermanic District
16th Street Viaduct over the Menomonee River Expansion Joint Replacement (BR100250110): (City Share Non-assessable Structure Fund - $75,000). The total estimated cost for this project is $675,000. This project is anticipated to be completed during the 2026 construction season.
16th Street Viaduct over the Menomonee River (BR100250111): In Dep...