Number
121677
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of permanent street lighting in conjunction with the reconstruction of the Lake Interchange and Hoan Bridge and related mitigation improvements under Federal and State Aid construction in the 4th Aldermanic District at a total estimated cost of $103,185.26, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of permanent street lighting in conjunction with the reconstruction of the Lake Interchange and Hoan Bridge, and for related mitigation improvements in the 4th Aldermanic District. The total estimated cost of this work is $103,185.26, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation. This resolution also authorizes the Commissioner of Public Works to install these improvements upon execution of the agreement, and authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total cost associated with all phases of the Lake Interchange Project for installation or modification of temporary and permanent street lighting and traffic control facilities is $616,000, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Body
Whereas, The Wisconsin Department of Transportation is reconstructing the Hoan Bridge, the Lake Interchange, and portions of IH 794; and
Whereas, Preliminary engineering work by City of Milwaukee was authorized under Common Council File Number 120707 for the improvements or modification of street lighting and traffic control devices on local streets associated with the Lake Interchange and Hoan Bridge Project; and
Whereas, The Lake Interchange and...
Click here for full text