Title
Resolution authorizing and directing the Commissioner of Public Works to execute a Revised Project Agreement titled “State/Municipal Agreement for a Highway Improvement Project” with the Wisconsin Department of Transportation for the rehabilitation of several local bridges with 80% Federal and/or State aid under the Local Bridge Replacement Program. (Infrastructure Services Division)
Analysis
This resolution authorizes and directs the Commissioner of Public Works to execute revised project agreements with the Wisconsin Department of Transportation (WISDOT) for the rehabilitation of several local bridges with Federal and/or State aid funding under the Local Bridge Replacement Program. The revised agreements will now include construction costs for the projects with 80% Federal and/or State Funds. The total estimated construction cost for the projects is $6,870,000 of which the City's share is $1,374,000. Construction funds will be included in a future Common Council resolution.
Body
Whereas, A project agreement has been executed by the WISDOT and the City of Milwaukee for the construction of the following bridge rehabilitation projects with Federal/State aid under the local bridge Replacement Program in accordance with Common Council Resolution File Number 991756, adopted on March 31, 2000.
1st Aldermanic District: North Teutonia Avenue Bridge over Union Pacific Railroad
1st Aldermanic District: North Teutonia Avenue Bridge over West Silver Spring Drive
14th Aldermanic District: East Lincoln Avenue Viaduct over Union Pacific Railroad
; and
Whereas, Preliminary engineering activities have begun and the construction costs for the bridge rehabilitation have increased from the original agreement; and
Whereas, Revised project agreements with the updated construction costs have been received from the WISDOT to be executed by the City of Milwaukee for the th...