powered help
header-left header-center header-right
File #: 972004    Version: 0
Type: Resolution Status: Passed
File created: 4/7/1998 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/5/1998
Effective date:    
Title: Resolution authorizing and directing the Commissioner of Public Works to execute two (2) documents titled "State/Municipal Agreement for a Preliminary Engineering Project" with the Wisconsin Department of Transportation for the programming and construction of the rehabilitation of two (2) bridge projects with Federal and/or State aid under the Local Bridge Replacement Program. (Infrastructure Services Div.)
Sponsors: THE CHAIR
Indexes: BRIDGES, HIGHWAYS, INTERGOVERNMENTAL AGREEMENTS, PUBLIC IMPROVEMENTS, TRANSPORTATION, WISCONSIN DEPARTMENT OF TRANSPORTATION
NUMB:
972004
VERS:
ORIGINAL
REF:

XXBY:
THE CHAIR
TITL:
Resolution authorizing and directing the Commissioner of Public Works to execute two (2) documents titled "State/Municipal Agreement for a Preliminary Engineering Project" with the Wisconsin Department of Transportation for the programming and construction of the rehabilitation of two (2) bridge projects with Federal and/or State aid under the Local Bridge Replacement Program. (Infrastructure Services Div.)
ANLS:


- Analysis -

This resolution authorizes the Commissioner of Public Works to execute two (2) documents titled "State/Municipal Agreement for a Preliminary Engineering Project" with the Wisconsin Department of Transportation for the programming and construction of the rehabilitation of two (2) bridge projects with Federal and/or State aid under the Local Bridge Replacement Program. The bridges are: West Cherry Street Bridge over the Milwaukee River and West Kilbourn Avenue Bridge over the Milwaukee River. The agreements will allow the projects to be undertaken with 80 percent Federal and/or State funds for preliminary engineering and construction costs. This resolution establishes the necessary subaccounts for preliminary engineering for the two (2) projects. The total estimated preliminary engineering cost is $622,000, of which the City's share is $124,400.


BODY:
Whereas, Preliminary approval for preliminary engineering has been requested and received from the Wisconsin Department of Transportation (WISDOT) along with agreements to be executed by the City of Milwaukee for the programming and construction of the rehabilitation of the following projects with Federal and/or State aid under the Local Bridge Replacement Program:

Aldermanic District Project Location

3&4 West Cherry Street Bridge Over the Milwaukee River

4 West Kilbourn Avenue Bridge over the Milwaukee River

and

Whereas, Further Federal and/or State participation for construction of the afor...