File #: 091235    Version:
Type: Resolution Status: Passed
File created: 1/20/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/9/2010
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,272,000 for a total estimated cost of these projects being $3,422,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Fiscal note, 2. Cover Letter, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
2/16/20101 MAYOR SIGNED   Action details Meeting details Not available
2/9/20101 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/27/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works, Infra. Services
Pass5:0 Action details Meeting details Not available
1/22/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
1/20/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
091235
Version
SUBSTITUTE 1
Reference
080237
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,272,000 for a total estimated cost of these projects being $3,422,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $3,272,000. The total estimated cost of these projects is $3,422,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

3rd Aldermanic District

E. North Ave. - N. Oakland Ave. to N. Cambridge Ave. (SM495080048) File Number 080237: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $716,000). The total estimated cost for this project including the requested amount is $736,000. This project is anticipated to be completed during the 2010 construction season.

N. Oakland Ave. - 150 feet m/l south of E. Hampshire St. to 260 feet m/l north of E. Hampshire St. (SM495080024) File Number 080911: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $98,000). The total estimated cost for this project including the requested amount is $113,000. This project is anticipated to be completed during the 2010 construction season.

N. Oakland Ave. - E. North Ave. to E. Thomas Ave. (SM495070106) File Number 080911: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $72,000). The total estimated cost for this project including the requested amount is $82,000. This project is...