powered help
header-left header-center header-right
File #: 211600    Version:
Type: Resolution Status: Passed
File created: 2/8/2022 In control: COMMON COUNCIL
On agenda: Final action: 3/1/2022
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $139,500 for a total estimated cost of these projects being $11,117,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
211600
Version
Substitute 1
Sponsor
THE CHAIR
Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $139,500 for a total estimated cost of these projects being $11,117,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $139,500 with the total cost estimated to be $11,117,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st and 4th Aldermanic Districts

N. 27th St. and W. Highland Ave. (SM499220012) Bioretention Maintenance Contract. (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2022 construction season.

6th Aldermanic District

E./W. Ring St. - N. Achilles St. to N. 2nd St. (SM495220011) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000) The total estimated cost of this project including the requested amount is $174,000. This project is anticipated to be completed during the 2022 construction season.

7th and 15th Aldermanic Districts

N. Sherman Blvd. (SM499220013) Bioretention Maintenance Contract. (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2022 construction season.