Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $9,525,237.20 for a total estimated cost of $16,499,000.00.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing notice list, 2. Official notice 28, 3. Official Notice Number 28 actions taken by Public Works committee, 4. Fiscal Note, 5. Capital Grant Resolutions Certification from the Comptroller's Office, 6. Notice Published on 11-14-08
Number
080807
Version
SUBSTITUTE 1
Reference
041289
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $9,525,237.20 for a total estimated cost of $16,499,000.00.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $9,525,237.20. The total estimated cost of these projects is $16,499,000.00.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd, 5th and 10th Aldermanic Districts

N. 76th St. (STH 181) - W. Center St. to W. Appleton Ave. (Portions in the City of Wauwatosa) (ST320061001) (2140-11-70) File Number 041289: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding, grading, and tree removal where necessary. (Grantor Paving Non-Reimbursable Fund Milwaukee -- $7,401,775; Grantor Paving Non-Reimbursable Fund Wauwatosa -- $261,905; Grantor Paving Reimbursable Fund Milwaukee -- $1,155,520; Non-Assessable Paving Fund -- $629,700; Assessable Paving Fund -- $50,000; Grantor Reimbursable Paving Fund Wauwatosa -- $22,100). These funds are to be transferred to the construction account (ST320061010) (2140-11-70).

Previously authorized for bridge and street construction: $0.00

Current estimated cost of the total project prior to this resolution: ...