Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $982,000 for a total estimated cost of these projects being $1,216,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $982,000. The total estimated cost of these projects is $1,216,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
4th Aldermanic District
Intersection of N. Water St. and E. Clybourn St. (SM495260021) Combined sewer repair. (Nonassessable Sewer Maintenance Relay Fund -- $120,000). The total estimated cost of this project including the requested amount is $120,000. This project is anticipated to be completed during the 2026 construction season.
6th Aldermanic District
W. Concordia Ave. - N. 11th St. to N. 12th St. (SM495250043) File Number 251881: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $25,000, additional funds). The total estimated cost of this project including the requested amount is $132,000. This project is anticipated to be completed during the 2026 construction season.
10th Aldermanic District
N. 50th St. - W. State St. to 150’ +/- North of W. State St. (SM495260020) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $185,000). The total estimated cost for this project including the requested amount is $185,000. This project is anticipated to be completed during ...