Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $2,831,205 for a total estimated cost of $3,380,405.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $2,831,205. The total estimated cost of these projects is $3,380,405.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
1st Aldermanic District
N. Teutonia Ave. - W. Capitol Dr. to W. Ruby Ave. (ST320120701) (2080-00-01) File Number 111507: Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, tree removal where necessary, sodding (6 - 15-foot width tree border area), and grading.
Grantor Non-Reimbursable Paving Fund -- $1,465,043
Grantor Reimbursable Paving Fund -- $219,757
City Share Non-assessable Paving Fund -- $1,043,605
City Share Assessable Paving Fund - $20,000
These funds are to be transferred to the construction account (ST3201207XX)
(2080-00-71).
Previously authorized for project construction: $0
Current estimated cost of total project including this resolution: $3,288,405
Original estimated cost of the project: $2,671,000
This project is anticipated to be completed during the 2015 construction season.
7th Aldermanic District
Alley between W....
Click here for full text