File #: 031392    Version:
Type: Resolution Status: Passed
File created: 1/21/2004 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/10/2004
Effective date:    
Title: Substitute resolution authorizing and directing the Commissioner of Public Works to enter into an Agreement with the Wisconsin Department of Transportation for the development, implementation and funding of traffic control and other safety measures necessary to mitigate traffic diversion on City streets due to construction activity on the Marquette Interchange in 2004.
Sponsors: THE CHAIR
Indexes: EXPRESSWAYS, INTERGOVERNMENTAL AGREEMENTS, PUBLIC IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter.pdf, 2. Fiscal Note.pdf, 3. Agreement.PDF, 4. Fiscal Review Analysis.pdf
Number
031392
Version
SUBSTITUTE
Reference
Sponsor
THE CHAIR
Title
Substitute resolution authorizing and directing the Commissioner of Public Works to enter into an Agreement with the Wisconsin Department of Transportation for the development, implementation and funding of traffic control and other safety measures necessary to mitigate traffic diversion on City streets due to construction activity on the Marquette Interchange in 2004.
Analysis
This resolution authorizes and directs the Commissioner of Public Works to execute an agreement with the Wisconsin Department of Transportation to provide reimbursement of actual costs for services and items provided by the City as traffic mitigation measures in conjunction with the reconstruction of the Marquette Interchange in 2004.
Body
Whereas, The Wisconsin Department of Transportation (WISDOT) will be undertaking the reconstruction of West Clybourn Street/West Tory Hill and the North 16th Street bridge over I-94 near the Marquette Interchange in 2004; and

Whereas, Construction activity on the Marquette Interchange is anticipated to result in the diversion of traffic on the local street system during this project due to long term street closures; and

Whereas, Preliminary approval has been received from the WISDOT, along with Project Agreements to be executed by the City of Milwaukee, to provide reimbursement of actual costs for necessary services and items provided by the City as local street traffic impact mitigation measures in conjunction with the Marquette Interchange construction; and

Whereas, The total estimated cost of local street traffic mitigation measures during the 2004 reconstruction of the Marquette Interchange is $285,786 including $190,851 for surface street traffic flow and operational improvements by the Department of Public Works, and $94,935 for priority control for fire emergency vehicles at traffic signals along key alternate routes; now, therefore, be it

Resolve...

Click here for full text