powered help
header-left header-center header-right
File #: 221516    Version: 0
Type: Resolution Status: Passed
File created: 2/7/2023 In control: COMMON COUNCIL
On agenda: Final action: 2/28/2023
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute documents titled “State/Municipal Agreement for a State-Let Local Bridge Project” with the Wisconsin Department of Transportation for the rehabilitation of the 35th Street Bridge over Pierce Street Phase 1 and the rehabilitation of the 35th Street Bridge over Pierce Street Phase 2, and to set up funds for design engineering at an estimated total cost of $1,502,883 with an estimated City share of $300,576 and a grantor share of $1,202,307.
Sponsors: THE CHAIR
Indexes: BRIDGES, INTERGOVERNMENTAL AGREEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. 2100-05-01_71 35th CMilw.pdf, 2. 2100-05-02_72 35th CMilw.pdf, 3. Resolution Certification 2100-05-01 221516, 4. Resolution Certification 2100-05-02 221516.pdf
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
3/2/20230 MAYOR SIGNED   Action details Meeting details Not available
2/28/20230 COMMON COUNCIL ADOPTEDPass11:0 Action details Meeting details Not available
2/15/20230 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Jonathan Thomas - DPW - said that this project will be done on 2026-2027
Pass5:0 Action details Meeting details Video Video
2/7/20230 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
221516
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution directing the Commissioner of Public Works to execute documents titled “State/Municipal Agreement for a State-Let Local Bridge Project” with the Wisconsin Department of Transportation for the rehabilitation of the 35th Street Bridge over Pierce Street Phase 1 and the rehabilitation of the 35th Street Bridge over Pierce Street Phase 2, and to set up funds for design engineering at an estimated total cost of $1,502,883 with an estimated City share of $300,576 and a grantor share of $1,202,307.
Analysis
This Resolution also authorizes the Commissioner of Public Works to execute a Project Agreement with the WisDOT for rehabilitation of the 35th Street Bridge over Pierce Street Phase 1 and the rehabilitation of the 35th Street Bridge over Pierce Street Phase 2. This resolution also directs the City Comptroller to transfer funds for preliminary engineering for these projects. The estimated total cost of the projects is $13,698,381 with an estimated City share of $2,764,796 and a grantor share of $10,933,585. The estimated preliminary engineering costs for these projects are $1,502,883 with an estimated City share of $300,576 and a grantor share of $1,202,307. Construction funds for these projects will be included in future resolutions.
Body
Whereas, A project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, and construction of the following bridge rehabilitations with Federal and State aid under the Local Bridge Program:

State I.D. 2100-05-01, 71
35th Street Bridge Phase 1
Over Pierce Street

State I.D. 2100-05-02, 72
35th Street Bridge Phase 2
Over Pierce Street

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

Wherea...

Click here for full text