5/13/2024 | 0 |
HISTORIC PRESERVATION COMMISSION
| ADOPTED
Minutes note: Mr. Tim Askin said the church requests to shorten a decorative parapet on an addition. The main church was built in 1917 and the addition at the rear was built by CG Schmidt in 1954 and is fairly minimal and inconsequential. The addition is a secondary piece to the overall church; this congregation cannot afford the full restoration at this time. Staff recommends re-build four courses above what they are proposing, but the triangle detail can be removed.
Pastor Kenneth Cutler - the cost difference to flatten it out versus build it back with a peak is about $7,000. They are willing to build it up four courses, but would like the flat roof. He will check with CG Schmidt to see about their doing the work.
Approve with conditions detailed in the staff report. | Pass | 6:0 |