Number
130014
Version
ORIGINAL
Reference
Sponsor
CHAIR
Title
Resolution relative to the cost participation and installation of temporary and permanent street lighting facilities in conjunction with Phase 1of Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $172,274.68 with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of temporary and permanent street lighting improvements in conjunction with Phase 1 Federal and State Aid construction as part of the Zoo Interchange Project in the 10th Aldermanic District. The total estimated cost of this project is $172,274.68, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation. This Resolution authorizes the Commissioner of Public Works to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project.
Body
Whereas, The Wisconsin Department of Transportation will be reconstructing the Zoo Interchange at IH 94, IH 894, and USH 45; and
Whereas, Preliminary engineering work by City of Milwaukee street lighting, traffic signals, and traffic signs staff was authorized under Common Council File Number 111184; and
Whereas, The Zoo Interchange project provides cost participation for work by the City of Milwaukee for street lighting improvements in conjunction with construction that impacts street lighting facilities under the jurisdiction of the City of Milwaukee; and
Whereas, Phase 1 construction for the Zoo Interchange reconstruction project will include the reconfiguration of West Kearney Street from South 84th Street to South 76th Street, install...
Click here for full text