powered help
header-left header-center header-right
File #: 080809    Version:
Type: Resolution Status: Passed
File created: 10/7/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 10/29/2008
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $120,000 for a total estimated cost of these projects being $2,471,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing notice list, 2. Fiscal Note
Number
080809
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $120,000 for a total estimated cost of these projects being $2,471,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $120,000 with the total cost estimated to be $2,471,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

N. Downer Ave. - E. Locust St. to E. Kenwood Blvd. (SM495070103) File Number 071055: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000 Additional Funds). The total estimated cost for this project including the requested amount is $421,000. This project is anticipated to be completed during the 2009 construction season.

N. Prospect Ave. - 180 feet m/l south of E. Park Pl. to E. Kenwood Blvd. (SM495070063) File Number 070266: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000 Additional Funds). The total estimated cost for this project including the requested amount is $687,000. This project is anticipated to be completed during the 2009 construction season.

8th Aldermanic District

W. Canal St. Viaduct Drainage Adjustment - W. Greves St. to a point 250 feet west (ST211080150): Downspouts, grading, construction of a new trap catch basin. The total estimated cost for this project is $33,100. This project is anticipated to be completed during the 2008 construction season.

W. Forest H...