powered help
header-left header-center header-right
File #: 111282    Version:
Type: Resolution Status: Passed
File created: 1/18/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/7/2012
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $380,000 for a total estimated cost of these projects being $16,709,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SANITARY SEWERS, SEWER IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
111282
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $380,000 for a total estimated cost of these projects being $16,709,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $380,000 with the total cost estimated to be $16,709,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

2nd and 7th Aldermanic Districts

Area bounded by W. Capitol Dr., W. Congress St., N. Sherman Blvd., and N. 51st St. (#11) (SM494120202): Sanitary sewer lining. (Infiltration/Inflow Reduction Fund -- $20,000). The total estimated cost for this project including the requested amount is $500,000. This project is anticipated to be completed during the 2012 construction season.

Area bounded by N. 51st St., N. 60th St., W. Keefe Ave., and W. Capitol Dr. (#10) (SM494120203): Sanitary sewer lining. (Infiltration/Inflow Reduction Fund -- $15,000). The total estimated cost for this project including the requested amount is $6,363,000. This project is anticipated to be completed during the 2012 construction season.

2nd and 10th Aldermanic Districts

Area bounded by W. Congress St., W. Melvina St., N. 60th St., and N. 65th St. (#8) (SM494120205): Sanitary sewer lining. (Infiltration/Inflow Reduction Fund -- $15,000). The total estimated cost for this project including the requested amount is $904,000. This project is anticipated to be completed during the 2012 const...