Number
241969
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design of North Holton Street with East Keefe Avenue, East Concordia Avenue, and East Burleigh Street with a total estimated cost increase for the project of $80,000, with an estimated Grantor share of $0, and an estimated City share of $80,000.
Analysis
Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the design of North Holton Street with East Keefe Avenue, East Concordia Avenue, and East Burleigh Streets with a total estimated cost increase for the project of $80,000, with an estimated Grantor share of $0, and an estimated City share of $80,000.
Body
Whereas, Additional funds are, therefore, necessary to complete the design of the projects; now, therefore be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:
Project Grant Value
State ID 2984-38-02
ST320241301
North Holton Street
East Keefe, East Concordia, and East Burleigh Streets
City Share Non-Assessable Paving Fund
ST320250000
Fund 0333
$80,000
Grantor Reimbursable
SP032250100
Fund 0306
$0
Grantor Non-Reimbursable
$0
Estimated Additional Design - $80,000
Total design previously authorized $231,750
Current estimated cost of total project including this resolution $1,779,613
Original estimated cost of total project (Resolution File Number 240372) $1,699,613
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
DAVID J TAPIA:C. Ciano
April 10, 2025