Number
100495
Version
ORIGINAL
Reference
100494
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,629,534 for a total estimated cost of these projects being $7,927,379.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,629,534. The total estimated cost of these projects is $7,927,379.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
3rd Aldermanic District
1311 E. Chambers St. (WT450075600): Riverside Pumps 6A and 6B Contract (C641090047). (Nonassessable Water Fund - $200,000, Additional Funds). The total estimated cost for this project including the requested amount is $833,845. This project is anticipated to be completed during the 2011 construction season.
N. Maryland Ave. - N. Prospect Ave. to a point north of N. Prospect Ave. (ST211100161) File Number 100494: Concrete curb and gutter. (Nonassessable Reconstruction Paving Fund -- $35,000). The total estimated cost for this project including the requested amount is $36,000. This project is anticipated to be completed during the 2010 construction season.
E. North Ave. Sink Hole (SM495100160) File Number 100494: (Nonassessable Sewer Maintenance Relay Fund -- $999,000). The total estimated cost for this project including the requested amount is $1,000,000. This project is anticipated to be completed during the 2010 construction season.
4th Aldermanic District
E. Buffalo St....
Click here for full text