powered help
header-left header-center header-right
File #: 170020    Version:
Type: Resolution Status: Passed
File created: 4/18/2017 In control: COMMON COUNCIL
On agenda: Final action: 5/9/2017
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,103,500 for a total estimated cost of these projects being $6,791,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
170020
Version
Substitute 1
Reference
151521
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,103,500 for a total estimated cost of these projects being $6,791,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,103,500. The total estimated cost of these projects is $6,791,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd Aldermanic District

N. 60thSt. - W. Glendale Ave. to W. Lincoln Creek Dr. (North) (WT410170621) File Number 151521: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $80,000). The total estimated cost for this project including the requested amount is $95,000. This project is anticipated to be completed during the 2017 construction season.

N. 76th St. - 290 feet south of W. Grantosa Dr. to W. Medford Ave. (SM495150084) File Number 160413: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $169,000, Additional Funds). The total estimated cost for this project including the requested amount is $194,000. This project was completed in 2016.

4th Aldermanic District

W. Michigan St. - N. 32nd St. to N. 33rd St. (ST214170105) File Number 170019: Install traffic calming speed hump(s). (Developer Paving Fund -- $5,000). The total estimated cost for this project including the requested amount is $7,000. This project is anticipated to be completed during...