powered help
header-left header-center header-right
File #: 200707    Version:
Type: Resolution Status: Passed
File created: 9/22/2020 In control: COMMON COUNCIL
On agenda: Final action: 10/13/2020
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $260,000 for a total estimated cost of these projects being $630,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number
200707
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $260,000 for a total estimated cost of these projects being $630,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $260,000 with the total cost estimated to be $630,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications: NPR

4th Aldermanic District

N. 9th St. - W. Wells St. to W. State St. (ST211200145) Install Walk and Curb and Gutter as necessary (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost of this project including the requested amount is $75,000. This project is anticipated to be completed during the 2020-21 construction season.

10th Aldermanic District

W. Center St. - N. 76th St. to N. 92nd St. (City of Wauwatosa Portion) (ST214200105) High Impact Asphalt Surface (Developer Paving Fund-- $180,000) The total estimated cost of this project including the requested amount is $355,000. This work was done in 2018. This resolution sets up the funds for the City of Wauwatosa portion.

11th Aldermanic District

W. Honey Creek Dr. - W. Morgan Ave. to W. River Bend Dr. (SM499200013) Bioswales. (Stormwater Quality - Non Assessable Water Quality Projects to meet TMDL Requirements, $15,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2021 construction seas...

Click here for full text