Number
090892
Version
ORIGINAL
Reference
971111
Sponsor
THE CHAIR
Title
Resolution authorizing the proper city officials to execute amended Utility Agreements with the State of Wisconsin, Department of Transportation for work on City of Milwaukee facilities in conjunction with the North-South Mitchell Interchange (Collector Distributor Roads/West Layton Avenue Contract), with a total estimated cost of $343,369.95, with an estimated Grantor’s share of $309,032.95 and an estimated City of Milwaukee share of $34,337.
Analysis
This resolution authorizes the Commissioner of Public Works and the Comptroller to execute the amended Utility Agreements Nos. 73, 74, 75, 76, 77, and 78 for Milwaukee Water Works, Environmental Engineering City of Milwaukee cable and City of Milwaukee conduit, for the utility work in conjunction with the North-South Mitchell Interchange (NSMI), with a total estimated cost of $343,369.95 with an estimated Grantor’s share of $309,032.95 and an estimated City of Milwaukee share of $34,337.
Body
Whereas, The State of Wisconsin, Department of Transportation (WISDOT) scheduled the rehabilitation of the North-South Mitchell Interchange (NSMI) in the City of Milwaukee; and
Whereas, The Department of Public Works (DPW) has worked with the WISDOT over the past year in planning the design and construction phasing of the project to best meet the needs of the citizens of the City of Milwaukee (CITY) and of the region as a whole; and
Whereas, Work on the NSMI has been phased in four major phases, being Phase I (South 27th Street; Airport Spur I; West Grange Avenue; West College Avenue) scheduled for 2009, Phase II (North Leg; West Layton Avenue; Airport Spur II) scheduled for 2010, and Phases III & IV (Mitchell Interchange) scheduled for 2011 and 2012; and
Whereas, There will be substantial work required on CITY utilities as a result of the design and construction associated with these NSMI contracts; and
Whereas, Wisconsin Statute 84.295(4m)...
Click here for full text