powered help
header-left header-center header-right
File #: 131076    Version:
Type: Resolution Status: Passed
File created: 11/26/2013 In control: COMMON COUNCIL
On agenda: Final action: 12/17/2013
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $240,000 for a total estimated cost of these projects being $5,107,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
131076
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $240,000 for a total estimated cost of these projects being $5,107,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $240,000 with the total cost estimated to be $5,107,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

Area bounded by W. Capitol Dr., W. Cornell St., N. Green Bay Ave., and N. 24th Pl. (SM494130206): Sanitary Sewer lining. (Infiltration/Inflow Reduction Fund -- $25,000). The total estimated cost for this project including the requested amount is $1,572,000. This project is anticipated to be completed during the 2014 construction season.

Area bounded by W. Hampton Ave., Lincoln Creek Pkwy., N. 23rd St., and N. Teutonia Ave. (SM494130208): Sanitary Sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project including the requested amount is $490,000. This project is anticipated to be completed during the 2014 construction season.

Area bounded by W. Villard Ave., W. Custer Ave., N. Sherman Blvd., and N. 51st Blvd. (SM494130207): Sanitary Sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project including the requested amount is $629,000. This project is anticipated to be completed during the 2014 construction season.

4th Alderma...

Click here for full text