Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,012,000 for a total estimated cost of $1,630,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. AD 9.pdf, 2. Ad signed.pdf, 3. Letter Signed.pdf, 4. AFR 9.pdf
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/10/20261 CITY CLERK PUBLISHED   Action details Meeting details Not available
3/26/20261 MAYOR SIGNED   Action details Meeting details Not available
3/24/20261 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
3/11/20261 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Ald. Bauman moved approval as amended. There were no objections.
Pass5:0 Action details Meeting details Not available
3/11/20260 PUBLIC WORKS COMMITTEE AMENDED

Minutes note: Appeared Holly Rutenbeck (DPW) 2nd Aldermanic District Alley between W. Fiebrantz Ave., W. Hope Ave., N. 62nd St., N. 63rd St. (ST212240109). Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. No public testimony. Ald. Bauman moved approval. There were no objections. 6th Aldermanic District Alley between W. Hopkins St., W. Townsend St., N. 22nd St., N. 23rd St. (ST 212220116). Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. No public testimony. Ald. Westmoreland moved approval. There were no objections. 8th Aldermanic District Alley between W. Greenfield Ave., W. Orchard St., S. 22nd St., S. 23rd St. (ST 212220107). Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. Patricia Doherty (LAS for Ald. Zamarripa) said they received an objection post card from one landlord. She added that Ald. Zamarripa is in full support of the project. Ald. Brower moved approval. There were no objections. 10th Aldermanic District W. Michigan St. — N. 35th St. to N. 37th St. (ext'd) (Including N. 36th St.- W. Michigan St. to W. Wisconsin Ave. (ST211240153). Concrete pavement reconstruction and asphalt pavement resurfacing, replace curb and gutter and sidewalk and driveway approaches where necessary, sodding (6 — 10 ft width tree border area) green infrastructure bioswales, and grading. No public testimony. Ald. Bauman moved approval. There were no objections. 15th Aldermanic District Alley between W. Fond du Lac Ave., W. Meinecke St., W. Wright St., N. 22nd St., N. 23rd St. (ST212220118). Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. No public testimony. Ald. Westmoreland moved approval. There were no objections.
   Action details Meeting details Video Video
3/3/20260 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
251879
Version
SUBSTITUTE
Reference
240145
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,012,000 for a total estimated cost of $1,630,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,012,000. The total estimated cost of these projects is $1,630,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd Aldermanic District

Alley between W. Fiebrantz Ave., W. Hope Ave., N. 62nd St., N. 63rd St. (ST212240109) File Number 240145: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. (Assessable Alley Paving Fund - $57,085; Nonassessable Alley Paving Fund -- $97,915). The total estimated cost for this project including the requested amount is $290,000. This project is anticipated to be completed during the 2026 construction season.

6th Aldermanic District

Alley between W. Hopkins St., W. Townsend St., N. 22nd St., N. 23rd St. (ST212220116) File Number 220870: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary. (Assessable Alley Paving Fund - $69,565; Nonassessable Alley Pavin...