Number
081588
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,105,000 for a total estimated cost of these projects being $17,476,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $1,105,000 with the total cost estimated to be $17,476,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
1st Aldermanic District
W. Congress St. - N. 17th St. to N. 18th St. (SM495090025): Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $67,000. This project is anticipated to be completed during the 2010 construction season.
W. Cornell St. - N. 22nd St. to N. 23rd St. (SM495090036): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $67,000. This project is anticipated to be completed during the 2009 construction season.
W. Eggert Pl. - N. 31st St. to N. Teutonia Ave. (SM495090027): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $90,000. This project is anticipated to be completed during the 2009 construction season.
Area bounded by W. Hampton Ave., W. Olive St., N. 17th St., and N. 24th Pl. (SM495090022): Sanitary sewer lining. (Nonasses...
Click here for full text