File #: 111225    Version: 0
Type: Resolution Status: Passed
File created: 1/18/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/7/2012
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic control devices in conjunction with the Federal/State Aid paving of North 20th Street from West Hopkins Street to West Capitol Drive in the 6th Aldermanic District at a total estimated cost of $119,885.97, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, STREET IMPROVEMENTS, TRAFFIC CONTROL SIGNALS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Comptroller's Certificate, 2. Cost Analysis, 3. Agreement, 4. Hearing Notice List
Number
111225
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of traffic control devices in conjunction with the Federal/State Aid paving of North 20th Street from West Hopkins Street to West Capitol Drive in the 6th Aldermanic District at a total estimated cost of $119,885.97, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of traffic control improvements in conjunction with the Federal/State Aid paving of North 20th Street from West Hopkins Street to West Capitol Drive in the 6th Aldermanic District at a total estimated cost of $119,885.97, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the entire project is $2,384,371.82, with a grantor share of $1,992,371.82 and a City share of $356,000.00.
Body
Whereas, The Project Agreement for the paving of North 20th Street from West Hopkins Street to West Capitol Drive was approved by the Common Council under File Number 110923; and

Whereas, The Surface Transportation Program provides cost participation for traffic control improvements in conjunction with the paving of highways located on the Federal/State Aid Highway System; and

Whereas, The total estimated cost of this project is $119,885.97 for the alteration and upgrade of traffic control signals and the upgrade of traffic control signs; and

Whereas, One hundred percent of the participating project cost is reimbursable from the Wisconsin Department of Transportation (WISDOT), and should be ea...