powered help
header-left header-center header-right
File #: 181228    Version:
Type: Resolution Status: Passed
File created: 11/27/2018 In control: COMMON COUNCIL
On agenda: Final action: 12/18/2018
Effective date:    
Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to $4,213,247 for a total estimated cost of these projects being $5,208,247.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Certification for NFR Monotube 181228.pdf
Number
181228
Version
SUBSTITUTE 1
Reference
171854
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to $4,213,247 for a total estimated cost of these projects being $5,208,247.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,213,247 The total estimated cost of these projects is $5,208,247.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

5th Aldermanic District

W. Burleigh St. - 50’ west of Burleigh St. Bridge to east side of W. Burleigh St. Bridge (SM495180092) Relaying storm sewer.
(Nonassessable Sewer Maintenance Relay Fund -- $38,000). The total estimated cost of this project including the requested amount is $48,000. This project is anticipated to be completed during the 2019 construction season.

N. 78th St. - W. Burleigh St. to W. Auer Ave. (WT410190680) File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 - $139,000). The total estimated cost for this project including the requested amount is $155,000. This project is anticipated to be completed during the 2019 construction season.

N. 79th St. - W. Auer Ave. to W. Lisbon Ave. (WT410190681) File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 - $199,000). The total estimated cost for this project including the req...

Click here for full text