powered help
header-left header-center header-right
File #: T232    Version: 0
Type: Travaux Resolution Status: Passed
File created: 1/24/2022 In control: TRAVAUX INC. BOARD OF DIRECTORS
On agenda: 1/27/2022 Final action: 1/27/2022
Effective date:    
Title: Resolution approving an award of contract to BYCO Incorporated (Mayville, WI) for flooring for Building 3.1 (Westlawn Renaissance V) at Westlawn Gardens Phase 2, in the amount of $355,000.00, Official Notice 58067
Sponsors: THE CHAIR
Attachments: 1. Bid Tab 58067-BYCO Inc-Flooring, 2. 3 .1 Final GMP-CORRECTED 01.25.2022
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/27/20220 TRAVAUX INC. BOARD OF DIRECTORS ADOPTED

Minutes note: Warren Jones, Travaux’s Vice President of Construction, stated that BYCO Incorporated has performed similar work for Travaux and has also provided 100% Minority Business Enterprise (MBE) participation for this contract.
Pass9:0 Action details Meeting details Not available
Number
232

Version
Original

Reference

Sponsor
The President

Title
Resolution approving an award of contract to BYCO Incorporated (Mayville, WI) for flooring for Building 3.1 (Westlawn Renaissance V) at Westlawn Gardens Phase 2, in the amount of $355,000.00, Official Notice 58067
Analysis

Body
WHEREAS, Travaux Inc. solicited sealed bids by Official Notice Number 58067 during the period December 1, 2021 through December 22, 2021 for Flooring for Building 3.1 (Westlawn Renaissance V) at Westlawn Gardens Phase 2; and

WHEREAS, two sealed bids were received by the deadline of 2:00 PM (CST) on December 22, 2021; and

WHEREAS, the sealed bids were received and publicly opened on December 22, 2021, during which the bidding procedure was conducted in compliance with the requirements of local, state, and federal regulations; and

WHEREAS, BYCO Inc., a qualified and competent bidder, submitted the lowest responsive and responsible bid in the amount of $355,000.00.; therefore, be it,

RESOLVED, by the Board of Directors of Travaux Inc. that it hereby authorizes and approves accepting the bid of and entering into a contract with BYCO Inc. for Flooring for Building 3.1 (Westlawn Renaissance V) at Westlawn Gardens Phase 2; and, be it

FURTHER RESOLVED, that funds for these services will come from Westlawn Renaissance V Mixed Financing; and, be it

FURTHER RESOLVED, that the proper officers of Travaux Inc. be and hereby are authorized and directed to properly execute said contract for and on behalf of Travaux Inc.; and, be it

FURTHER RESOLVED, that if any extensions of the time of performance are needed, the officers of Travaux Inc. may approve such request without any further action of the Board of Directors of Travaux Inc.; and, be it

FURTHER RESOLVED, that all of above is contingent upon receiving the approval of the U.S. Department of Housing and Urban Development, if it is determined that such approval is required; and, be it

FURTHER RESOLVED, that all a...

Click here for full text