powered help
header-left header-center header-right
File #: 991615    Version:
Type: Resolution Status: Passed
File created: 2/8/2000 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/29/2000
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, STREET IMPROVEMENTS, VIADUCTS
NUMB:
991615
VERS:
SUBSTITUTE 1
XXBY:
THE CHAIR
TITL:
Substitute resolution determining it necessary to make various assessable public improvements at various locations.
ANLS:
-Analysis-

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.
BODY:
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

2nd Aldermanic District

Alley between W. Chambers St., W. Girard Ave., N. 64th St., N. 66th St. (ST212010141): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $1,000)

3rd Aldermanic District

E. Belleview Pl. - N. Lake Dr. to N. Downer Ave. (ST211010145): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000)

E. Kenwood Blvd. - 800 feet m/l east of N. Lake Dr. to 150 feet m/l east of N. Lake Dr. (ST211010146): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000)

Alley between N. Jackson St., N. Jefferson St., E. Pleasant St., N. Water St. (Southerly 125 feet m/l) (ST212010140): Pav...