powered help
header-left header-center header-right
File #: 131377    Version:
Type: Resolution Status: Passed
File created: 1/22/2014 In control: COMMON COUNCIL
On agenda: Final action: 2/11/2014
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $6,667,155 for a total estimated cost of these projects being $8,975,263.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Comptrollers Certification, 2. Another Comptroller's Certificate, 3. Hearing Notice List
Number
131377
Version
Substitute 1
Reference
121332
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $6,667,155 for a total estimated cost of these projects being $8,975,263.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $6,667,155. The total estimated cost of these projects is $8,975,263.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

3rd Aldermanic District

N. Humboldt Blvd. - W. Clarke St. to W. Center St. (SM495130011) File Number 121332: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $108,000). The total estimated cost for this project including the requested amount is $120,000. This project is anticipated to be completed during the 2014 construction season.

3rd and 6th Aldermanic Districts

E. Hadley St. - N. Holton St. to N. Humboldt Blvd. (SM495130078) File Number 130688: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $1,200,000). The total estimated cost for this project including the requested amount is $1,220,000. This project is anticipated to be completed during the 2014 construction season.

N. Pierce St. - E. Hadley St. to E. Locust St. (SM495130042) File Number 130234: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $320,000). The total estimated cost for this project including the requested amount is $335,000. This project is ...