powered help
header-left header-center header-right
File #: 090778    Version: 0
Type: Resolution Status: Passed
File created: 10/13/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 11/3/2009
Effective date:    
Title: Resolution authorizing the Commissioner of Public Works to execute a Revised Project Agreement titled "State/Municipal Agreement for a Highway Improvement Project" between the City of Milwaukee and Wisconsin Department of Transportation associated with the rehabilitation of the West Hampton Avenue Bridge over Lincoln Creek with 80 percent Federal and/or State aid under the Local Bridge Rehabilitation Program.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, BRIDGES, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Revised State/Municipal Agreement, 2. Cover Letter, 3. Fiscal Note, 4. Fiscal Analysis, 5. Hearing Notice List
Number
090778
Version
ORIGINAL
Reference
060882
Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works to execute a Revised Project Agreement titled "State/Municipal Agreement for a Highway Improvement Project" between the City of Milwaukee and Wisconsin Department of Transportation associated with the rehabilitation of the West Hampton Avenue Bridge over Lincoln Creek with 80 percent Federal and/or State aid under the Local Bridge Rehabilitation Program.
Analysis
This resolution authorizes the Commissioner of Public Works to execute a Revised Project Agreement with the WISDOT associated with the rehabilitation of the West Hampton Avenue Bridge over Lincoln Creek. The Revised Project Agreement provides for 80 percent Federal/State aid and 20 percent local cost sharing for the increased construction costs for the project. The total estimated cost for the project is $1,825,690 of which $365,938 is the City of Milwaukee’s share and $1,459,752 is the grantor share. Construction funds will be requested in a future Common Council resolution.
Body
Whereas, The Common Council of the City of Milwaukee adopted Resolution File Number 060882 authorizing and directing the Commissioner of Public Works to execute an agreement with the Milwaukee and Wisconsin Department of Transportation (WISDOT) for rehabilitation of the West Hampton Avenue Bridge over Lincoln Creek with 80 percent Federal and/or State aid under the Local Bridge Rehabilitation Program; and

Whereas, As part of the preliminary engineering process, construction costs have been refined and increased since the original agreement was drafted three years ago; and

Whereas, The WISDOT has submitted a Revised Project Agreement that includes additional monies for the construction associated with the bridge rehabilitation for City execution; and

Whereas, This project is scheduled for construction in 2010 and construction funds for this project will be requested in a separate reso...